AngryData an hour ago

I mean that doesn't sound like very big hurdles. It is an inspection of a completed reactor to make sure it wasn't managed and built like trash. Every factory and business and powerplant is subject to an inspection before it can operate. Even most residentual homes require an inspection before people can live in it.

lazide an hour ago | parent [-]

It is what typically all reactors get stuck on for years - or often decades.

mpweiher an hour ago | parent [-]

I doubt it.

There used to be separate construction and operating permits, and sometimes you got the building permit, built the plant and then never got the operating license.

This has now been streamlined with a combined construction/operating license. If you built what you promised to build, you get to operate it.

devmor 40 minutes ago | parent [-]

Can you give an example of a plant that has been built under this streamlined process and what kind of timeline it had?

The only recent nuclear buildouts that I personally have knowledge of are expansions to existing plants and thus have a lower barrier to get going.

lazide 27 minutes ago | parent [-]

Since it was just released, that’s pretty hard to do eh?

I’m familiar with the reactors built on other previous ‘expedited’ processes that ended up being anything but fast. We’ll see how it goes eh?