▲ Kon5ole 2 hours ago

>The primary cost for nuclear is the initial construction.

That's a common claim but it's not really correct.

Firstly, the average plant in the US spends it's construction costs every 2-3 years, I assume the situation is similar in the EU. New power plants are much more expensive of course, because the old ones were built before Chernobyl, Fukushima, 9/11 and other incidents that revealed horrible security flaws in existing plants and procedures.

Secondly, the costs of handling Chernobyl are way, way higher than the total cost of construction for all nuclear plants in the EU combined. Similarly the cost of managing Fukushima is way higher than the cost of constructing all the nuclear plants in Japan. These costs are of course never added to the cost of nuclear power, since nobody operating nuclear plants has any chance of paying such sums. But they are in fact a larger factor than the construction costs were.

These experiences did have some effect, thankfully, in that made new power plants more expensive, because we know that we must take any conceivable measure to prevent more Chernobyls and Fukushimas from happening.

And thirdly, the reason why Sweden closed the two most recent reactors was cost, despite them being paid off a long time ago. Meaning there is significant cost even after the construction is paid.

So it seems that the claim that "construction is the main cost" comes from the operator's point of view. Basically "the construction is the largest part WE have to pay, because taxpayers cover the rest".

▲AnthonyMouse an hour ago | parent [-]

> That's a common claim but it's not really correct.

It's a common claim because it's correct.

> the average plant in the US spends it's construction costs every 2-3 years

That includes paying principal and interest on the construction loans, right?

> New power plants are much more expensive of course, because the old ones were built before Chernobyl, Fukushima, 9/11 and other incidents that revealed horrible security flaws in existing plants and procedures.

The modern cost increases have nothing to do with actual deficiencies in older US plants. Chernobyl had no containment building and a positive void coefficient. Even the US nuclear power plants build in the 1960s have a containment building and a negative void coefficient.

> Secondly, the costs of handling Chernobyl are way, way higher than the total cost of construction for all nuclear plants in the EU combined.

It's a good thing none of the US nuclear plants have ever been Soviet RBMKs then.

> And thirdly, the reason why Sweden closed the two most recent reactors was cost

The reason was that their electricity prices were very low at the time from a combination of having a large amount of hydro and the then-price of natural gas being low. Most places have no ability to control either of those things. Meanwhile how is the decision to close those reactors looking given how prices are now?