| ▲ | Terr_ 4 hours ago | |
> > Problems arise when people try to perma-peg [points to man-hours] > Upper management [...] only deal in the units of hours I feel you're mixing up different operations here. You can always express unfinished work as likely to require a certain number of team-sprints, which are convertible to theoretic man-hours. The key is that the conversation rate is only valid for a moment, and technically that moment was the prior sprint. That's very different from management thinking (or worse, declaring) that points have a permanently fixed proportion to man-hours. > [...] and dollars If your management deals in international currency, then perhaps that would be a useful analogy to them: Points and Man-Hours are different sides of FOREX, and they fluctuate based on different conditions. When Engineering predicts a group of tasks is 54 points, that's like a foreign company signing a long-term contract in €100 EUR instead of USD. You can estimate that you'll receive ~$112 USD in a year, but the actual dollars will likely be different because the exchange-rate will continue changing before that happens. | ||