| ▲ | whateverboat 3 hours ago | |
TSMC's Arizona fab needs 200MW of electricity. But even more importantly, they need 2 separate completely independent substation feeds, since a 15 second interruption can cause 0.1B Euro of losses. Finally, and here is where Europe really really suffers, generally you need these things to be planned, approved and built within a year. | ||