| ▲ | gehsty an hour ago | |
Failing to get a permit is not an act of god, having to pay even when the site does t have power is poor milestone / payment planning. Also it’s quite hard to request payment if the thing you are buying is not working (appreciate this quite complex here), but if the people who are delivering the data center are responsible for delivering the power, it feels like oracle would be within reason to not pay? | ||