| ▲ | nomel an hour ago | ||||||||||||||||
There's also a power generation water cost though! Something like 500g/MWh for gas/coal/nuclear (~70% of power in AZ), so a huge xAI datacenter (Colossus 2, ~1 GW/h) would use ~700 MW of this type, or ~350k gallons of water an hour, which would be 0.2% of the Colorado rivers flow rate last year. I don't know if that's significant. | |||||||||||||||||
| ▲ | derektank 26 minutes ago | parent [-] | ||||||||||||||||
Pulling recent data from the EIA, of the roughly 10,000 megawatts of new power capacity installed in Arizona between 2023 and 2025, 50% is batteries, 40% solar, 6.5% wind, and 3.5% gas. Now, most solar and wind plants rarely if ever hit their nameplate capacity, but it’s pretty clear the large majority of new power generation isn’t consuming water. https://www.eia.gov/electricity/data/eia860/ | |||||||||||||||||
| |||||||||||||||||