| ▲ | California Energy Storage System Survey(energy.ca.gov) | |
| 4 points by toomuchtodo 4 hours ago | 1 comments | ||
| ▲ | toomuchtodo 4 hours ago | parent [-] | |
Updated June 15th, 2026. Indicates 41% (~21GW) completed towards 2045 goal of 52GW of storage serving California’s CAISO electrical grid. At current deployment rates, California will likely reach their target ~10 years early (~2035). Does not appear to include the Nighthawk Energy Storage Project, a 300-megawatt (MW) / 1,200-megawatt-hour (MWh) battery facility in Poway, California, recently commissioned. https://interestingengineering.com/energy/1200-mwh-battery-f... https://www.nighthawkenergystorage.com/about-the-project/ CAISO Active Battery Project Queue: https://www.interconnection.fyi/?market=CAISO&status=Active&... (~94GW, does not include hybrid battery and generation projects) | ||