Mashimo 2 hours ago

These ones no construction had been started yet AFAIK.

If AI summery is to be trusted, a few other windparks got stopped that where almost done, but got completed anyway after a legal battle. Vineyard Wind 1, Coastal Virginia (CVOW), Empire Wind 1, Revolution Wind, Sunrise Wind.

Again, got it from AI, make of that what you want.

cwal37 2 hours ago | parent [-]

The feds have dropped their attempts to stop those from ongoing construction for now, but only one of those projects is complete.

CVOW is supposed to flow first power this month, but won't be done for ~a year, Empire Wind is also end of '26/early '27, Sunrise later in 2027.

Vineyard was completed this month, and Revolution is delivering power and targets completion over the next few months.