One option is to do multi-stage rollout of your database schema and code, over some time windows. I recall a blog post here (I think) lately from some Big Company (tm) that would run one step from the below plan every week:

1. Create new fields in the DB.

2. Make the code fill in the old fields and the new fields.

3. Make the code read from new fields.

4. Stop the code from filling old fields.

5. Remove the old fields.

Personally, I wouldn't use it until I really need it. But a simpler form is good: do the required schema changes (additive) iteratively, 1 iteration earlier than code changes. Do the destructive changes 1 iteration after your code stops using parts of the schema. There's opposite handling of things like "make non-nullable field nullable" and "make nullable field non-nullable", but that's part of the price of smooth operations.

Izkata 4 hours ago | parent [-]

2.5 (if relevant) mass-migrate data from the old column to the new column, so you don't have to wait forever.