▲ | onesociety2022 4 days ago | |
But that's assuming they actually have to transport power over long distances right? If they colocate these massive AI datacenters right next to the power generation plants, it should be cheap to transport the power. You don't need to upgrade massive sections of the grid and build long-distance power lines. The xAI Colossus 2 1GW data centers seem to be located about ~20 miles from the power generation utility (https://semianalysis.com/2025/09/16/xais-colossus-2-first-gi...) | ||
▲ | gehsty 4 days ago | parent [-] | |
20 miles is a long way to move power, on land you have huge issues over getting permits for construction as it’s so disruptive, offshore specialist vessels that serve a global existing supply chain. |