tuetuopay 3 days ago

We’ve had our share of anti-nuclear activists in France. The project got endlessly stalled, with shifting legislative grounds, and general opposition. Also, the general inefficiency and incompetence from Areva meant this was a match made in heaven (or hell, depends) to get nearly infinite delay.

pfdietz 3 days ago | parent [-]

Flamanville 3 failed because of screwups in the design and construction. What you're blaming the opposition for is exposing that and holding the nuclear people responsible. How dare they, right? /s

natmaka 2 days ago | parent [-]

> Flamanville 3 failed because of screwups in the design and construction

Indeed, and it is so undeniable that it is the official conclusion. Source (French): https://www.assemblee-nationale.fr/dyn/media/organes-parleme...