So the context of the quiz is software estimation, where I assume it's an intentional parable of estimating something you haven't seen before. It's trying to demonstrate that your "5-7 days" estimate probably represents far more certainty than you intended. For some of these, your answer could span orders of magnitude. E.g. my answer for the heaviest blue whale would probably be 5-500 tons because I don't have a good concept of things that weigh 500 tons. The important point is that I'm right around 9 times in 10, not that I had a precise estimate. | ||||||||||||||||||||
▲ | duckmysick 3 days ago | parent [-] | |||||||||||||||||||
I don't know, an estimate spanning three orders of magnitude doesn't seem useful. To continue your example of 5-7 days, it would turn into an estimate of 5-700 days. So somewhere between a week or two years. And fair enough, whatever you're estimating will land somewhere in between. But how do I proceed from there with actual planning or budget? | ||||||||||||||||||||
|