▲ | redleggedfrog 6 days ago | |||||||||||||||||||||||||||||||||||||
You can't make accurate estimates that can be used for deadlines for non-trivial work. You can make educated guesses on how long specific things will take, and it might be a pretty good guess if you've been keeping metrics on your past work, including things like vacation days and other similar disruptions as well, and keeping a team together long enough to have solid institutional knowledge on your code-base. And you can respectfully lay these numbers out to a manager in the form of, "This will probably take 1 to 3 days," or for bigger stuff, "2 to 3 weeks", and so on. And the manager can take the sum of all this and say, "The soonest it can probably be done is 3 months, but most likely it'll be 4, with a small chance of a bit longer", or whatever, you get the idea. And then the mangers can set the deadline as they see fit. Now, for some reason, many managers just look at the first number and are done - that's the due date. And then after that they get deer in the headlights treatment, so the worst case becomes the best case. That's on them. If they don't understand that software estimation isn't an exact science they're in the wrong field. As for software development being special, I really hope that what I've described above is like other engineering disciplines, and we're not special. I don't want to be special, I want to be an engineer, like those who work with aircraft or bridges and what not. I feel like in those fields the concept of estimation is a little more respected. But I'm probably wrong. :^) I'll mention I've been a professional software developer since the early 90's, not that experience equals veracity. But I've had good success using the system above, and even though the bad managers to good managers was pretty even during that time, the company experienced outstanding success during my tenure (20 years!). In the end, bad managers never last. Good managers, who take reasonable estimates to their superiors, succeeded, where managers who brought "It'll be done July 1st" got doubted because their superiors know it really doesn't work that way. | ||||||||||||||||||||||||||||||||||||||
▲ | bdangubic 6 days ago | parent [-] | |||||||||||||||||||||||||||||||||||||
your comment is exactly what I am talking about. you actually CAN make accurate estimates for non-trivial works. try to envision this - I hand you a non-trivial assignment to estimate with a condition that if you meet your estimate -/+ 5% you get 7-figure bonus. alternatively if you do not you get fired. after working 30 years in the biz you tell me which of the two is happening for you? I worked at two places that gave huge bonuses when deadlines were met (based on “estimates”) and wouldn’t you know it sh*t always got done on time and people got paid. | ||||||||||||||||||||||||||||||||||||||
|